The Main Section of the Dhaka Elevated Expressway Project by the South Asia Branch has Achieved Complete Connectivity for the Opening of the Road
On the evening of May 24th, with the successful placement of the final T-beam for sections P308-P309 of the Dhaka Elevated Expressway Project in Bangladesh, the main section of the road has achieved complete connectivity for opening.

This main section of the road is 4526 meters in length and includes 348 piers, 353 bridge spans, and 2272 T-beams. Throughout the construction process, the project team overcame various challenges such as densely populated construction areas, the need to work around existing railways, and the impact of the COVID-19 pandemic. Through collaborative efforts, they successfully pushed the project forward, taking a significant step towards achieving the partial opening goal.

Moving forward, the South Asia branch will continue to act as a trailblazer, aligning with the themes of the thematic education campaign on Xi Jinping Thought on Socialism with Chinese Characteristics for a New Era. They will prioritize practical action, strive for new accomplishments, and fully contribute to the creation of high-quality projects under the Belt and Road Initiative. This dedication will support the substantial international growth of the Company and make valuable contributions to China’s overseas infrastructure endeavors.eir improved quality of life. Ambassador Ma expressed the hope for the timely completion of the entire road project.